πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

ONSHORE WIND Β· MISO

Onshore wind project J1004, Mecosta County

Onshore wind project J1004, Mecosta County is a 800 MW onshore wind request withdrawn in the MISO interconnection queue, in Mecosta County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedNov 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1004
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Kenowa - Nelson Road 345kV Line Tap
Location
Mecosta County, Michigan
Technology
Wind: 800 MW
Total requested
800 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 March 2018
Proposed online date
September 2020
Withdrawn
November 2018

Location

Marker shows the centre of Mecosta County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Mecosta County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem