Onshore wind project J1048, Mecosta County

Onshore wind project J1048, Mecosta County is a 250 MW onshore wind request withdrawn in the MISO interconnection queue, in Mecosta County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedMar 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1048
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Vergennes - Nelson Road 345kV Line Tap
Location
Mecosta County, Michigan
Technology
Wind: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 March 2018
Proposed online date
September 2020
Withdrawn
March 2019

Location

Marker shows the centre of Mecosta County; the queue data does not give exact sites.