United States βΊ Grid βΊ Interconnection queues βΊ Illinois
ONSHORE WIND Β· MISOOnshore wind project J974, Fulton County
Onshore wind project J974, Fulton County is a 250 MW onshore wind request withdrawn in the MISO interconnection queue, in Fulton County, Illinois, connecting to AMEREN ILLINOIS.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2018 (completed)
- Withdrawn / abandonedJun 2025 (project stopped here)
- ConsentedOct 2021 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J974
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- Mapleridge 345kV Switching Station
- Location
- Fulton County, Illinois
- Technology
- Wind: 250 MW
- Total requested
- 250 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 12 March 2018
- Agreement signed
- 12 October 2021
- Proposed online date
- October 2023
- Withdrawn
- June 2025
Location
Marker shows the centre of Fulton County; the queue data does not give exact sites.
Other requests in Fulton County
- Solar project J1383, Fulton CountySolar Β· 150 MW Β· agreement signed
- Solar + storage project J1199, Fulton CountySolar + storage Β· 20.0 MW Β· agreement signed
- Solar project J2186, Fulton CountySolar Β· 821 MW Β· in study
- Solar + storage project J2390, Fulton CountySolar + storage Β· 350 MW Β· in study
- Battery storage project J4199, Fulton CountyBattery storage Β· 200 MW Β· in study
- Solar project J3167, Fulton CountySolar Β· 180 MW Β· in study
- Coal project J046, Fulton CountyCoal Β· 31.0 MW Β· built
- Coal project G868, Fulton CountyCoal Β· 23.0 MW Β· built
- Coal project G535, Fulton CountyCoal Β· 16.0 MW Β· built
- Coal project G367, Fulton CountyCoal Β· 800 MW Β· withdrawn
- Solar project J3349, Fulton CountySolar Β· 400 MW Β· withdrawn
- Solar project J3240, Fulton CountySolar Β· 150 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem