SOLAR · MISO

Solar project J1383, Fulton County

Solar project J1383, Fulton County is a 150 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Fulton County, Illinois, connecting to AMEREN ILLINOIS.

Queue statusConsented
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedAug 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1383
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN ILLINOIS
Connection point (POI)
Ipava 138 kV Substation
Location
Fulton County, Illinois
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Active
Entered queue
29 April 2019
Agreement signed
29 August 2025
Proposed online date
June 2025

Location

Marker shows the centre of Fulton County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Fulton County