SOLAR Β· MISO

Solar project J1020, Jasper County

Solar project J1020, Jasper County is a 250 MW solar request withdrawn in the MISO interconnection queue, in Jasper County, Mississippi, connecting to COOPERATIVE ENERGY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedJan 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1020
Grid region
MISO (Midcontinent)
Utility / transmission owner
COOPERATIVE ENERGY
Connection point (POI)
Missionary 230kV Substation
Location
Jasper County, Mississippi
Technology
Solar: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 March 2018
Proposed online date
September 2022
Withdrawn
January 2020

Location

Marker shows the centre of Jasper County; the queue data does not give exact sites.

Power plants in Mississippi Β· Transmission lines in Mississippi

Other requests in Jasper County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem