United States βΊ Grid βΊ Interconnection queues βΊ Mississippi
SOLAR + STORAGE Β· SOUTHEASTSolar + storage project IC-1031, Jasper County
Solar + storage project IC-1031, Jasper County is a 150 MW solar + storage request withdrawn in the Southeast interconnection queue, in Jasper County, Mississippi, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2022 (completed)
- Withdrawn / abandonedApr 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-1031
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Jasper East SS Substation 230 kV Bus
- Location
- Jasper County, Mississippi
- Technology
- Solar: 150 MW Β· Battery
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 11 March 2022
- Proposed online date
- August 2025
- Withdrawn
- April 2025
Location
Marker shows the centre of Jasper County; the queue data does not give exact sites.
Power plants in Mississippi Β· Transmission lines in Mississippi
Other requests in Jasper County
- Solar project IC-1145, Jasper CountySolar Β· 156 MW Β· agreement signed
- Solar project IC-1203, Jasper CountySolar Β· 44.0 MW Β· agreement signed
- Solar + storage project J1946, Jasper CountySolar + storage Β· 350 MW Β· in study
- Solar project 25-IC-1355, Jasper CountySolar Β· 165 MW Β· in study
- Solar project J1020, Jasper CountySolar Β· 250 MW Β· withdrawn
- Solar + storage project IC-1205, Jasper CountySolar + storage Β· 200 MW Β· withdrawn
- Solar + storage project J3108, Jasper CountySolar + storage Β· 180 MW Β· withdrawn
- Solar project IC-707, Jasper CountySolar Β· 160 MW Β· withdrawn
- Solar + storage project IC-Pachuta Solar, Jasper CountySolar + storage Β· 160 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem