SOLAR + STORAGE Β· SOUTHEAST

Solar + storage project IC-Pachuta Solar, Jasper County

Solar + storage project IC-Pachuta Solar, Jasper County is a 160 MW solar + storage request withdrawn in the Southeast interconnection queue, in Jasper County, Mississippi, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. Planning (completed)
  2. Withdrawn / abandonedDec 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-Pachuta Solar
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Jasper East - Enterprise 230 kV Line
Location
Jasper County, Mississippi
Technology
Solar: 160 MW Β· Battery
Total requested
160 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Withdrawn
December 2021

Location

Marker shows the centre of Jasper County; the queue data does not give exact sites.

Power plants in Mississippi Β· Transmission lines in Mississippi

Other requests in Jasper County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem