SOLAR Β· MISO

Solar project J1009, Kenosha County

Solar project J1009, Kenosha County is a 400 MW solar request withdrawn in the MISO interconnection queue, in Kenosha County, Wisconsin, connecting to American Transmission Co..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedMay 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1009
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
Pleasant Prairie - Racine 345kV Line Tap
Location
Kenosha County, Wisconsin
Technology
Solar: 400 MW
Total requested
400 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 March 2018
Proposed online date
September 2020
Withdrawn
May 2020

Location

Marker shows the centre of Kenosha County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in Kenosha County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem