πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in ISO-NE (New England)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown458,609 MW
Active in queue14.6 GW72 requests
Agreement signed8,609 MW45 requests
Withdrawn982118.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

45 requests
ProjectCapacityStatusLocationRegionQueuedOnline
SouthCoast Wind 1
Offshore wind
1,200 MWAgreement signed MAISO-NE Apr 2021target 2031
Bay State Wind 4 Offshore Wind
Offshore wind
1,200 MWAgreement signed MAISO-NE Dec 2019target 2033
Vineyard Offshore Wind
Offshore wind
800 MWAgreement signed MAISO-NE Nov 2016target 2026
Park City Offshore Wind
Offshore wind
791 MWAgreement signed MAISO-NE Dec 2017target 2029
Revoultion Offshore wind
Offshore wind
704 MWAgreement signed RIISO-NE Sep 2018target 2026
Battery Storage
Battery storage
508 MWAgreement signed Middlesex, MAISO-NE Jun 2021target 2028
Lite Brite Battery Storage
Battery storage
306 MWAgreement signed Suffolk, MAISO-NE Jul 2021target 2028
Medway Grid Battery Storage
Battery storage
250 MWAgreement signed Norfolk, MAISO-NE Mar 2019target 2025
Hecate Energy Eastern Ave Energy Center
Battery storage
250 MWAgreement signed Suffolk, MAISO-NE Apr 2021target 2026
Naugatuck Avenue Battery Storage
Battery storage
205 MWAgreement signed New Haven, CTISO-NE Jan 2021target 2027
Battery Storage
Battery storage
205 MWAgreement signed Washington, RIISO-NE Sep 2021target 2029
Norman Street Battery Storage
Battery storage
204 MWAgreement signed Middlesex, MAISO-NE Mar 2021target 2028
Battery Storage
Battery storage
204 MWAgreement signed Worcester, MAISO-NE Oct 2022target 2027
Green Apple Solar
Solar
179 MWAgreement signed Androscoggin, MEISO-NE Feb 2021target 2027
Energy Storage
Battery storage
170 MWAgreement signed Norfolk, MAISO-NE Apr 2019target 2027
Solar
Solar
165 MWAgreement signed Somerset, MEISO-NE Feb 2021target 2029
Battery Storage Addition (to QP1086)
Solar + storage
160 MWAgreement signed Knox, MEISO-NE May 2022target 2026
Solar
Solar
150 MWAgreement signed Hartford, CTISO-NE Mar 2022target 2028
Battery Storage
Battery storage
142 MWAgreement signed Litchfield, CTISO-NE Oct 2022target 2029
Broadleaf Solar
Solar
101 MWAgreement signed Hartford, CTISO-NE Nov 2021target 2027
Three Rivers Solar
Solar
100 MWAgreement signed Hancock, MEISO-NE Jan 2019target 2026
Warren Meadow Solar
Solar
74.5 MWAgreement signed Knox, MEISO-NE Nov 2020target 2026
Ocean State Power uprate
Gas
73.2 MWAgreement signed Providence, RIISO-NE Apr 2018target 2026
Bear Swamp Unit 1 and 2 Upgrade
Battery storage
66.0 MWAgreement signed Berkshire, MAISO-NE Jan 2016target 2023
Husky Solar
Solar
50.2 MWAgreement signed Windham, CTISO-NE Jun 2021target 2029
FPS Panton Solar
Solar
50.0 MWAgreement signed Addison, VTISO-NE Dec 2018target 2027
West Springfield 45 MW BESS
Battery storage
45.0 MWAgreement signed Hampden, MAISO-NE Jun 2022target 2029
Solar Knox
Solar
33.5 MWAgreement signed Knox, MEISO-NE Oct 2021target 2027
Nutes Solar
Solar
20.0 MWAgreement signed Strafford, NHISO-NE May 2021target 2026
Fair Haven Solar
Solar
20.0 MWAgreement signed Rutland, VTISO-NE Aug 2017target 2027
Shaftsbury Solar
Solar
20.0 MWAgreement signed Bennington, VTISO-NE Jul 2017target 2028
BD Solar Church Hill
Solar
20.0 MWAgreement signed Androscoggin, MEISO-NE Feb 2020target 2028
GDC Saco Solar
Solar
20.0 MWAgreement signed York, MEISO-NE Oct 2019target 2027
Turner Meadow Solar
Solar
19.8 MWAgreement signed Androscoggin, MEISO-NE Jun 2021target 2026
Twin Energy Wind
Onshore wind
18.3 MWAgreement signed Oxford, MEISO-NE Oct 2021target 2026
SolarFairfield
Solar
18.1 MWAgreement signed Somerset, MEISO-NE Dec 2020target 2027
West Baldwin Solar
Solar
17.1 MWAgreement signed Cumberland, MEISO-NE Oct 2019target 2029
Emery Meadow Solar
Solar
16.4 MWAgreement signed York, MEISO-NE Apr 2020target 2027
Solar
Solar
7.0 MWAgreement signed Kennebec, MEISO-NE Aug 2019target 2022
Solar
Solar
6.8 MWAgreement signed Plymouth, MAISO-NE Jan 2018target 2019
Battery addition
Other
6.7 MWAgreement signed Franklin, MAISO-NE Aug 2021target 2027
Grissom Solar
Solar
5.0 MWAgreement signed Sullivan, NHISO-NE Mar 2022target 2026
Berkshire Wind Increase
Onshore wind
4.6 MWAgreement signed Berkshire, MAISO-NE Aug 2012target 2019
Roxbury Solar
Solar
2.0 MWAgreement signed Oxford, MEISO-NE Oct 2021target 2026
NEA Bell. Uprate (Northeast Energy Associates, LP)
Gas
1.4 MWAgreement signed Norfolk, MAISO-NE Mar 2015target 2018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)