Interconnection queue in Nevada — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24981.5 GW
Active in queue81.5 GW249 requests
Agreement signed20.9 GW82 requests
Withdrawn35588.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

249 requests · page 3 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Company JX, Pershing County
Solar + storage
340 MWPaused / redesign Pershing, NVWest Sep 2019target 2023
Dandelion Hybrid Solar
Solar + storage
334 MWIn study Nye, NVCAISO Apr 2021target 2027
Serenity
Solar
305 MWIn study Nye, NVCAISO Apr 2023target 2031
Roccasecca BESS
Battery storage
303 MWAgreement signed Clark, NVCAISO May 2016target 2026
Battery storage project Company 213, Clark County
Battery storage
300 MWPaused / redesign Clark, NVWest Mar 2022target 2029
Solar + storage project Company MB, White Pine County
Solar + storage
300 MWAgreement signed White Pine, NVWest Sep 2021target 2028
Solar + storage project Company MT, White Pine County
Solar + storage
300 MWPaused / redesign White Pine, NVWest Mar 2022target 2030
Solar + storage project Company 225, Clark County
Solar + storage
300 MWPaused / redesign Clark, NVWest Sep 2022target 2030
Solar + storage project Company 189, Clark County
Solar + storage
300 MWPaused / redesign Clark, NVWest Feb 2020target 2025
Solar + storage project Company LL, Pershing County
Solar + storage
300 MWPaused / redesign Pershing, NVWest Mar 2021target 2029
Solar + storage project Company MA, White Pine County
Solar + storage
300 MWAgreement signed White Pine, NVWest Sep 2021target 2028
Solar + storage project Company MH, Churchill County
Solar + storage
300 MWAgreement signed Churchill, NVWest Sep 2021target 2024
Solar + storage project Company NS, Eureka County
Solar + storage
300 MWPaused / redesign Eureka, NVWest Sep 2022target 2029
Onshore wind project Company NA, White Pine County
Onshore wind
300 MWPaused / redesign White Pine, NVWest Mar 2022target 2030
Solar + storage project Company MJ, Lyon County
Solar + storage
300 MWPaused / redesign Lyon, NVWest Sep 2021target 2029
Solar + storage project Company 165, Clark County
Solar + storage
300 MWAgreement signed Clark, NVWest Sep 2018target 2026
Solar + storage project Company MU, White Pine County
Solar + storage
300 MWPaused / redesign White Pine, NVWest Mar 2022target 2030
Solar + storage project Company ND, Lander County
Solar + storage
300 MWPaused / redesign Lander, NVWest Mar 2022target 2030
Tahoe
Battery storage
300 MWAgreement signed Clark, NVCAISO May 2016target 2026
Solar + storage project Company PR, Esmeralda County
Solar + storage
300 MWIn study Esmeralda, NVWest Mar 2023target 2026
Battery storage project Company 219, Clark County
Battery storage
300 MWPaused / redesign Clark, NVWest Mar 2022target 2029
Solar + storage project Company 195, Clark County
Solar + storage
275 MWAgreement signed Clark, NVWest Mar 2021target 2023
Delamar Energy Storage 2
Battery storage
256 MWIn study Clark, NVCAISO Apr 2021target 2027
Delamar Energy Storage
Battery storage
256 MWAgreement signed Clark, NVCAISO Apr 2020target 2027
Other project Company KW, White Pine County
Other
250 MWPaused / redesign White Pine, NVWest Sep 2020target 2026
Battery storage project Company 237, Clark County
Battery storage
250 MWAgreement signed Clark, NVWest Jan 2023target 2026
Battery storage project 25-00431, Storey County
Battery storage
250 MWIn study Storey, NVWest Jul 2025target 2029
Battery storage project Company 217, Clark County
Battery storage
250 MWPaused / redesign Clark, NVWest Mar 2022target 2029
Solar + storage project NC5-003, Clark County
Solar + storage
250 MWIn study Clark, NVWest Aug 2017target 2022
Solar + storage project Company KN, Humboldt County
Solar + storage
250 MWAgreement signed Humboldt, NVWest Aug 2020target 2024
Battery storage project Company NZ, Storey County
Battery storage
250 MWPaused / redesign Storey, NVWest Sep 2022target 2030
Solar project Company 170, Clark County
Solar
250 MWPaused / redesign Clark, NVWest Sep 2018target 2023
Solar + storage project Company QX, Churchill County
Solar + storage
240 MWIn study Churchill, NVWest Mar 2024target 2028
Solar + storage project Company HQ, Pershing County
Solar + storage
240 MWPaused / redesign Pershing, NVWest Sep 2017target 2024
Geothermal project Company LM, Lyon County
Geothermal
230 MWAgreement signed Lyon, NVWest Mar 2021target 2029
Gas project Company 230, Clark County
Gas
222 MWAgreement signed Clark, NVWest Sep 2022target 2024
Gas project Company 231, Clark County
Gas
222 MWAgreement signed Clark, NVWest Sep 2022target 2024
Battery storage project Company 211, Clark County
Battery storage
220 MWAgreement signed Clark, NVWest Jan 2022target 2029
Gas project Company QF, Humboldt County
Gas
218 MWIn study Humboldt, NVWest Sep 2023target 2026
Gas project Company QG, Humboldt County
Gas
218 MWIn study Humboldt, NVWest Sep 2023target 2026
Container
Solar
205 MWIn study Nye, NVCAISO Apr 2023target 2031
Grapevine 1
Solar
205 MWIn study Nye, NVCAISO Apr 2023target 2031
Nelson Hills
Solar
205 MWIn study Nye, NVCAISO Apr 2023target 2031
Solar + storage project Company LK, Lyon County
Solar + storage
200 MWAgreement signed Lyon, NVWest Mar 2021target 2029
Solar + storage project Company 208, Clark County
Solar + storage
200 MWPaused / redesign Clark, NVWest Sep 2021target 2025
Solar + storage project Company LG, Lyon County
Solar + storage
200 MWAgreement signed Lyon, NVWest Mar 2021target 2029
Solar + storage project Company LD, Lander County
Solar + storage
200 MWPaused / redesign Lander, NVWest Mar 2021target 2029
Solar + storage project NC5-005, Clark County
Solar + storage
200 MWIn study Clark, NVWest May 2018target 2021
Geothermal project 25-00405, Churchill County
Geothermal
200 MWIn study Churchill, NVWest Jul 2025target 2029
Battery storage project Company 248, Clark County
Battery storage
200 MWAgreement signed Clark, NVWest Mar 2023target 2030

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)