BATTERY STORAGE · CAISO

Delamar Energy Storage 2

Delamar Energy Storage 2 is a 256 MW battery storage request in interconnection study in the CAISO interconnection queue, in Clark County, Nevada, connecting to SCE.

Queue statusIn planning
  1. PlanningQueued Apr 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
2141
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
SCE portion of Eldorado Substation 230 kV
Location
Clark County, Nevada
Technology
Battery: 256 MW
Total requested
256 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
15 April 2021
Proposed online date
June 2027

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Clark County