Solar + storage project Company 189, Clark County

Solar + storage project Company 189, Clark County is a 300 MW solar + storage request suspended in the West interconnection queue, in Clark County, Nevada, connecting to NV Energy.

Queue statusPaused / redesign
  1. PlanningQueued Feb 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Company 189
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Clark County, Nevada
Technology
Solar: 300 MW · Battery
Total requested
300 MW
Service type
Network resource (NRIS)
Queue status
Suspended
Entered queue
5 February 2020
Proposed online date
March 2025

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Clark County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem