Gas project GI-2006-1d, Weld County Gas |
269 MW | Agreement signed |
Weld, CO | West |
Jan 2006 | target 2007 |
Battery storage project 5RSC-2024-11, Morgan County Battery storage |
250 MW | In study |
Morgan, CO | West |
Jan 2024 | target 2027 |
Solar + storage project GI-2018-24, Pueblo County Solar + storage |
250 MW | Agreement signed |
Pueblo, CO | West |
Aug 2018 | 2022 |
Gas project 22-07251, Larimer County Gas |
250 MW | In study |
Larimer, CO | West |
Jul 2022 | target 2028 |
Solar + storage project GI-2024-16, Kiowa County Solar + storage |
250 MW | In study |
Kiowa, CO | West |
May 2024 | target 2027 |
Solar + storage project 5RSC-2024-27, Morgan County Solar + storage |
250 MW | In study |
Morgan, CO | West |
Jan 2024 | target 2026 |
Onshore wind project GI-2007-13, Lincoln County Onshore wind |
250 MW | Agreement signed |
Lincoln, CO | West |
Nov 2007 | target 2009 |
Battery storage project 5RSC-2024-10, Cheyenne County Battery storage |
250 MW | In study |
Cheyenne, CO | West |
Jan 2024 | target 2027 |
Onshore wind project GI-2007-12, El Paso County Onshore wind |
250 MW | Agreement signed |
El Paso, CO | West |
Nov 2007 | target 2010 |
Solar + storage project 2RSC-2020-05, Pueblo County Solar + storage |
250 MW | Agreement signed |
Pueblo, CO | West |
Sep 2020 | target 2022 |
Solar project GI-2019-6, Pueblo County Solar |
240 MW | In study |
Pueblo, CO | West |
May 2019 | 2021 |
Onshore wind project GI-2004-2, Baca County Onshore wind |
238 MW | Agreement signed |
Baca, CO | West |
Feb 2004 | |
Solar + storage project GI-DISIS-2022-04, Kit Carson County Solar + storage |
237 MW | Agreement signed |
Kit Carson, CO | West |
May 2022 | target 2027 |
Solar + storage project GI-2020-10, Pueblo County Solar + storage |
230 MW | Paused / redesign |
Pueblo, CO | West |
Apr 2020 | target 2023 |
Solar project GI-TC-2024-17, Kit Carson County Solar |
225 MW | In study |
Kit Carson, CO | West |
May 2024 | target 2030 |
Solar + storage project GI-DISIS-2022-49, Prowers County Solar + storage |
225 MW | Paused / redesign |
Prowers, CO | West |
May 2022 | target 2029 |
Onshore wind project GI-CS-2025-24, Kit Carson County Onshore wind |
225 MW | In study |
Kit Carson, CO | West |
Sep 2025 | target 2029 |
Solar project GI-TC-2024-28, Weld County Solar |
222 MW | In study |
Weld, CO | West |
May 2023 | target 2027 |
Solar project GI-TC-2024-14, Weld County Solar |
206 MW | In study |
Weld, CO | West |
May 2023 | target 2028 |
Onshore wind project GI-2013-5, Arapahoe County Onshore wind |
201 MW | Agreement signed |
Arapahoe, CO | West |
Jul 2013 | 2014 |
Solar project BHCT G29, Pueblo County Solar · 174 Power Global |
200 MW | Paused / redesign |
Pueblo, CO | West |
Aug 2020 | target 2023 |
Wind + storage project 22-07252, Larimer County Wind + storage |
200 MW | In study |
Larimer, CO | West |
Jul 2022 | target 2026 |
Onshore wind project 3RSC-2023-03, Kiowa County Onshore wind |
200 MW | In study |
Kiowa, CO | West |
May 2023 | target 2025 |
Battery storage project 5RSC-2024-12, Pueblo County Battery storage |
200 MW | In study |
Pueblo, CO | West |
Jan 2024 | target 2027 |
Battery storage project 5RSC-2024-09, Park County Battery storage |
200 MW | In study |
Park, CO | West |
Jan 2024 | target 2027 |
Gas project 5RSC-2024-01, Weld County Gas |
200 MW | In study |
Weld, CO | West |
Jan 2024 | target 2027 |
Battery storage project GI-SISS-2025-06, Logan County Battery storage |
200 MW | In study |
Logan, CO | West |
Oct 2025 | target 2027 |
Onshore wind project GI-2006-2, Logan County Onshore wind |
200 MW | Agreement signed |
Logan, CO | West |
Jun 2006 | target 2008 |
Onshore wind project GI-2011-7, Lincoln County Onshore wind |
200 MW | Agreement signed |
Lincoln, CO | West |
Aug 2011 | target 2012 |
Onshore wind project GI-2007-6, Weld County Onshore wind |
200 MW | Agreement signed |
Weld, CO | West |
Mar 2007 | target 2008 |
Battery storage project GI-RSC-2025-02, Moffat County Battery storage |
200 MW | In study |
Moffat, CO | West |
Jul 2025 | target 2029 |
Solar project 3RSC-2023-01, Pueblo County Solar |
200 MW | In study |
Pueblo, CO | West |
May 2023 | target 2025 |
Solar project 5RSC-2024-23, Pueblo County Solar |
200 MW | In study |
Pueblo, CO | West |
Jan 2024 | target 2028 |
Battery storage project GI-2011-2 & 7, Arapahoe County Battery storage |
200 MW | Paused / redesign |
Arapahoe, CO | West |
Sep 2022 | target 2025 |
Onshore wind project GI-2016-15, Lincoln County Onshore wind |
200 MW | Paused / redesign |
Lincoln, CO | West |
Jul 2016 | target 2020 |
Solar project BHCT G49, Pueblo County Solar |
200 MW | In study |
Pueblo, CO | West |
Jun 2024 | target 2026 |
Solar + storage project CSU-2020-3, El Paso County Solar + storage |
200 MW | In study |
El Paso, CO | West |
Jun 2020 | target 2025 |
Onshore wind project GI-2011-2, Lincoln County Onshore wind |
200 MW | Agreement signed |
Lincoln, CO | West |
Mar 2011 | target 2012 |
Solar + storage project GI-CS-2025-20, Morgan County Solar + storage |
200 MW | In study |
Morgan, CO | West |
Sep 2025 | target 2029 |
Onshore wind project GI-DISIS-2022-29, Lincoln County Onshore wind |
200 MW | Agreement signed |
Lincoln, CO | West |
May 2022 | target 2029 |
Solar + storage project GI-CS-2025-19, Morgan County Solar + storage |
200 MW | In study |
Morgan, CO | West |
Sep 2025 | target 2029 |
Solar + storage project GI-CS-2025-17, Moffat County Solar + storage |
200 MW | In study |
Moffat, CO | West |
Sep 2025 | target 2029 |
Solar + storage project GI-TC-2024-26, Elbert County Solar + storage |
199 MW | In study |
Elbert, CO | West |
May 2023 | target 2027 |
Solar + storage project GI-2024-01, Weld County Solar + storage |
199 MW | In study |
Weld, CO | West |
Apr 2024 | target 2027 |
Solar + storage project 5RSC-2024-24, Adams County Solar + storage |
199 MW | In study |
Adams, CO | West |
Jan 2024 | target 2027 |
Onshore wind project GI-CS-2025-07, Kit Carson County Onshore wind |
199 MW | In study |
Kit Carson, CO | West |
Sep 2025 | target 2029 |
Solar + storage project GI-CS-2025-02, Adams County Solar + storage |
199 MW | In study |
Adams, CO | West |
Sep 2025 | target 2031 |
Solar + storage project BHCT G33, Pueblo County Solar + storage |
199 MW | In study |
Pueblo, CO | West |
Jun 2022 | target 2025 |
Solar project GI-2020-01, Pueblo County Solar |
199 MW | Paused / redesign |
Pueblo, CO | West |
Mar 2020 | target 2023 |
Onshore wind project GI-DISIS-2021-07, Prowers County Onshore wind |
199 MW | Paused / redesign |
Prowers, CO | West |
May 2021 | target 2026 |