Requests shown20943.2 GW
Active in queue43.2 GW209 requests
Agreement signed11.0 GW60 requests
Withdrawn36875.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

209 requests · page 2 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GI-2006-1d, Weld County
Gas
269 MWAgreement signed Weld, COWest Jan 2006target 2007
Battery storage project 5RSC-2024-11, Morgan County
Battery storage
250 MWIn study Morgan, COWest Jan 2024target 2027
Solar + storage project GI-2018-24, Pueblo County
Solar + storage
250 MWAgreement signed Pueblo, COWest Aug 20182022
Gas project 22-07251, Larimer County
Gas
250 MWIn study Larimer, COWest Jul 2022target 2028
Solar + storage project GI-2024-16, Kiowa County
Solar + storage
250 MWIn study Kiowa, COWest May 2024target 2027
Solar + storage project 5RSC-2024-27, Morgan County
Solar + storage
250 MWIn study Morgan, COWest Jan 2024target 2026
Onshore wind project GI-2007-13, Lincoln County
Onshore wind
250 MWAgreement signed Lincoln, COWest Nov 2007target 2009
Battery storage project 5RSC-2024-10, Cheyenne County
Battery storage
250 MWIn study Cheyenne, COWest Jan 2024target 2027
Onshore wind project GI-2007-12, El Paso County
Onshore wind
250 MWAgreement signed El Paso, COWest Nov 2007target 2010
Solar + storage project 2RSC-2020-05, Pueblo County
Solar + storage
250 MWAgreement signed Pueblo, COWest Sep 2020target 2022
Solar project GI-2019-6, Pueblo County
Solar
240 MWIn study Pueblo, COWest May 20192021
Onshore wind project GI-2004-2, Baca County
Onshore wind
238 MWAgreement signed Baca, COWest Feb 2004
Solar + storage project GI-DISIS-2022-04, Kit Carson County
Solar + storage
237 MWAgreement signed Kit Carson, COWest May 2022target 2027
Solar + storage project GI-2020-10, Pueblo County
Solar + storage
230 MWPaused / redesign Pueblo, COWest Apr 2020target 2023
Solar project GI-TC-2024-17, Kit Carson County
Solar
225 MWIn study Kit Carson, COWest May 2024target 2030
Solar + storage project GI-DISIS-2022-49, Prowers County
Solar + storage
225 MWPaused / redesign Prowers, COWest May 2022target 2029
Onshore wind project GI-CS-2025-24, Kit Carson County
Onshore wind
225 MWIn study Kit Carson, COWest Sep 2025target 2029
Solar project GI-TC-2024-28, Weld County
Solar
222 MWIn study Weld, COWest May 2023target 2027
Solar project GI-TC-2024-14, Weld County
Solar
206 MWIn study Weld, COWest May 2023target 2028
Onshore wind project GI-2013-5, Arapahoe County
Onshore wind
201 MWAgreement signed Arapahoe, COWest Jul 20132014
Solar project BHCT G29, Pueblo County
Solar · 174 Power Global
200 MWPaused / redesign Pueblo, COWest Aug 2020target 2023
Wind + storage project 22-07252, Larimer County
Wind + storage
200 MWIn study Larimer, COWest Jul 2022target 2026
Onshore wind project 3RSC-2023-03, Kiowa County
Onshore wind
200 MWIn study Kiowa, COWest May 2023target 2025
Battery storage project 5RSC-2024-12, Pueblo County
Battery storage
200 MWIn study Pueblo, COWest Jan 2024target 2027
Battery storage project 5RSC-2024-09, Park County
Battery storage
200 MWIn study Park, COWest Jan 2024target 2027
Gas project 5RSC-2024-01, Weld County
Gas
200 MWIn study Weld, COWest Jan 2024target 2027
Battery storage project GI-SISS-2025-06, Logan County
Battery storage
200 MWIn study Logan, COWest Oct 2025target 2027
Onshore wind project GI-2006-2, Logan County
Onshore wind
200 MWAgreement signed Logan, COWest Jun 2006target 2008
Onshore wind project GI-2011-7, Lincoln County
Onshore wind
200 MWAgreement signed Lincoln, COWest Aug 2011target 2012
Onshore wind project GI-2007-6, Weld County
Onshore wind
200 MWAgreement signed Weld, COWest Mar 2007target 2008
Battery storage project GI-RSC-2025-02, Moffat County
Battery storage
200 MWIn study Moffat, COWest Jul 2025target 2029
Solar project 3RSC-2023-01, Pueblo County
Solar
200 MWIn study Pueblo, COWest May 2023target 2025
Solar project 5RSC-2024-23, Pueblo County
Solar
200 MWIn study Pueblo, COWest Jan 2024target 2028
Battery storage project GI-2011-2 & 7, Arapahoe County
Battery storage
200 MWPaused / redesign Arapahoe, COWest Sep 2022target 2025
Onshore wind project GI-2016-15, Lincoln County
Onshore wind
200 MWPaused / redesign Lincoln, COWest Jul 2016target 2020
Solar project BHCT G49, Pueblo County
Solar
200 MWIn study Pueblo, COWest Jun 2024target 2026
Solar + storage project CSU-2020-3, El Paso County
Solar + storage
200 MWIn study El Paso, COWest Jun 2020target 2025
Onshore wind project GI-2011-2, Lincoln County
Onshore wind
200 MWAgreement signed Lincoln, COWest Mar 2011target 2012
Solar + storage project GI-CS-2025-20, Morgan County
Solar + storage
200 MWIn study Morgan, COWest Sep 2025target 2029
Onshore wind project GI-DISIS-2022-29, Lincoln County
Onshore wind
200 MWAgreement signed Lincoln, COWest May 2022target 2029
Solar + storage project GI-CS-2025-19, Morgan County
Solar + storage
200 MWIn study Morgan, COWest Sep 2025target 2029
Solar + storage project GI-CS-2025-17, Moffat County
Solar + storage
200 MWIn study Moffat, COWest Sep 2025target 2029
Solar + storage project GI-TC-2024-26, Elbert County
Solar + storage
199 MWIn study Elbert, COWest May 2023target 2027
Solar + storage project GI-2024-01, Weld County
Solar + storage
199 MWIn study Weld, COWest Apr 2024target 2027
Solar + storage project 5RSC-2024-24, Adams County
Solar + storage
199 MWIn study Adams, COWest Jan 2024target 2027
Onshore wind project GI-CS-2025-07, Kit Carson County
Onshore wind
199 MWIn study Kit Carson, COWest Sep 2025target 2029
Solar + storage project GI-CS-2025-02, Adams County
Solar + storage
199 MWIn study Adams, COWest Sep 2025target 2031
Solar + storage project BHCT G33, Pueblo County
Solar + storage
199 MWIn study Pueblo, COWest Jun 2022target 2025
Solar project GI-2020-01, Pueblo County
Solar
199 MWPaused / redesign Pueblo, COWest Mar 2020target 2023
Onshore wind project GI-DISIS-2021-07, Prowers County
Onshore wind
199 MWPaused / redesign Prowers, COWest May 2021target 2026

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20102025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)