Solar project BHCT G29, Pueblo County

Solar project BHCT G29, Pueblo County is a 200 MW solar request suspended in the West interconnection queue, in Pueblo County, Colorado, connecting to Black Hills Colorado Electric.

Queue statusPaused / redesign
  1. PlanningQueued Aug 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
BHCT G29
Grid region
West (non-ISO utilities)
Utility / transmission owner
Black Hills Colorado Electric
Developer
174 Power Global
Connection point (POI)
Pueblo West – North Penrose 115kV
Location
Pueblo County, Colorado
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
LGIA Executed/Suspended
Queue status
Suspended
Entered queue
28 August 2020
Proposed online date
March 2023

Location

Marker shows the centre of Pueblo County; the queue data does not give exact sites.

Power plants in Colorado · Transmission lines in Colorado

Other requests in Pueblo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem