United States › Grid › Interconnection queues › Colorado

ONSHORE WIND · WEST

Onshore wind project GI-2007-13, Lincoln County

Onshore wind project GI-2007-13, Lincoln County is a 250 MW onshore wind request with a signed interconnection agreement in the West interconnection queue, in Lincoln County, Colorado, connecting to Public Service Company Of Colorado.

Queue statusConsented
  1. PlanningQueued Nov 2007 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2009 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GI-2007-13
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company Of Colorado
Connection point (POI)
Pawnee-Daniels Park 230kV Line
Location
Lincoln County, Colorado
Technology
Wind: 250 MW
Total requested
250 MW
Service type
NRIS and ERIS
Study phase
Feasibility/System Impact Study complete Facilities Study complete LGIA signed
Queue status
Active
Entered queue
14 November 2007
Proposed online date
December 2009

Location

Marker shows the centre of Lincoln County; the queue data does not give exact sites.

Power plants in Colorado · Transmission lines in Colorado

Other requests in Lincoln County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem