🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Colorado

SOLAR + STORAGE · WEST

Solar + storage project GI-2024-20, Lincoln County

Solar + storage project GI-2024-20, Lincoln County is a 199 MW solar + storage request in interconnection study in the West interconnection queue, in Lincoln County, Colorado, connecting to Public Service Company Of Colorado.

Queue statusIn planning
  1. PlanningQueued May 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GI-2024-20
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company Of Colorado
Connection point (POI)
Pronghorn-Missile Site 345 kV line
Location
Lincoln County, Colorado
Technology
Solar: 199 MW · Battery
Total requested
199 MW
Service type
Energy only (ERIS)
Study phase
Detailed status: Study to be started after completion of 5RSC
Queue status
Active
Entered queue
17 May 2024
Proposed online date
May 2028

Location

Marker shows the centre of Lincoln County; the queue data does not give exact sites.

Power plants in Colorado · Transmission lines in Colorado

Other requests in Lincoln County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem