Solar + storage project GI-2020-10, Pueblo County

Solar + storage project GI-2020-10, Pueblo County is a 230 MW solar + storage request suspended in the West interconnection queue, in Pueblo County, Colorado, connecting to Public Service Company Of Colorado.

Queue statusPaused / redesign
  1. PlanningQueued Apr 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GI-2020-10
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company Of Colorado
Connection point (POI)
Comanche-Midway 230 kV line
Location
Pueblo County, Colorado
Technology
Solar: 230 MW · Battery
Total requested
230 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Phase 4 Report Completed 03/31/2022 Phase 2 Re-Study Report Completed 12/28/2022; Detailed status: LG
Queue status
Suspended
Entered queue
7 April 2020
Proposed online date
December 2023

Location

Marker shows the centre of Pueblo County; the queue data does not give exact sites.

Power plants in Colorado · Transmission lines in Colorado

Other requests in Pueblo County