Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,248140.4 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,248 requests · page 14 of 25
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AI2-231A, Botetourt County
Battery storage
60.0 MWIn study Botetourt, VAPJM Mar 2023target 2023
Pigeon Run Solar and Storage
Solar · Pigeon Run Solar, LLC
60.0 MWAgreement signed Campbell, VAPJM Mar 2019target 2031
Solar project AI2-024, Meigs County
Solar
60.0 MWIn study Meigs, OHPJM Dec 2022target 2028
Mora Solar
Solar
60.0 MWAgreement signed Carbon, PAPJM Sep 2020target 2027
Lafayette Storage
Battery storage · Lafayette Energy, LLC
60.0 MWIn study Fayette, PAPJM Jan 2025target 2024
Solar + storage project AI2-444
Solar + storage
59.5 MWIn study WVPJM Mar 2023target 2026
Solar project AI1-123, Lunenburg County
Solar
59.0 MWIn study Lunenburg, VAPJM Sep 2022target 2026
Carnation
Solar
58.0 MWAgreement signed Fairfield, OHPJM Sep 2020target 2028
Blossom Solar
Solar
56.0 MWAgreement signed Morrow, OHPJM Jun 2020target 2027
Morgnec Road Solar
Solar
55.8 MWAgreement signed Kent, MDPJM Apr 2016target 2025
Solar project AI2-245, Woodford County
Solar
55.2 MWIn study Woodford, ILPJM Mar 2023target 2028
Dover Solar Facility
Solar
55.0 MWPaused / redesign Whitley, INPJM Mar 2019target 2026
Battery storage project AG2-272, Pittsylvania County
Battery storage · Tupelo Storage, LLC
55.0 MWIn study Pittsylvania, VAPJM Feb 2025target 2024
Hardin Energy Center – Storage II
Battery storage
55.0 MWPaused / redesign Hardin, OHPJM Mar 2019target 2026
Solar project AG2-617, Anne Arundel County
Solar · Dairy Farm Solar, L.L.C.
55.0 MWIn study Anne Arundel, MDPJM Mar 2025target 2023
Bluestem Solar
Battery storage · RWE Solar Development, LLC
55.0 MWIn study Laporte, INPJM Sep 2020target 2023
Flat Run Solar
Solar
55.0 MWAgreement signed Barren, KYPJM Aug 2019target 2026
Solar project AI2-224, Charlotte County
Solar
55.0 MWIn study Charlotte, VAPJM Mar 2023target 2025
Battery storage project AH2-061, Prince William County
Battery storage
55.0 MWIn study Prince William, VAPJM Dec 2021target 2028
Solar project AG2-585, Kankakee County
Solar · Grand Marsh Solar 2, LLC
55.0 MWIn study Kankakee, ILPJM Mar 2025target 2024
Dover Solar
Solar
55.0 MWPaused / redesign York, PAPJM Mar 2019target 2026
Battery storage project AH2-060, Prince William County
Battery storage
55.0 MWIn study Prince William, VAPJM Dec 2021target 2027
Barrelhead
Solar · Barrelhead Solar, LLC
54.0 MWAgreement signed KYPJM Sep 2020target 2029
Gas project AH1-744, Prince George's County
Gas · Parkway Generation Operating LLC
53.5 MWIn study Prince George's, MDPJM Apr 2025
Solar project AI1-151, Adams County
Solar
53.2 MWIn study Adams, OHPJM Sep 2022target 2027
Gladys Solar
Solar · Gladys Solar, LLC
53.0 MWAgreement signed Campbell, VAPJM Mar 2019target 2031
Solar project AG2-073, Madison County
Solar · SR Madison, LLC
53.0 MWIn study Madison, KYPJM Mar 2025target 2024
Solar project AH2-080, Brunswick County
Solar
52.7 MWIn study Brunswick, VAPJM Jan 2022target 2025
Solar + storage project AH2-076, Perry County
Solar + storage
52.5 MWIn study Perry, KYPJM Jan 2022target 2023
Battery storage project AH2-145, King George County
Battery storage
52.3 MWIn study King George, VAPJM Feb 2022target 2027
Wythe County Solar Project
Battery storage
52.2 MWAgreement signed Wythe, VAPJM Mar 2019target 2027
Clermont County Solar Project
Battery storage
52.2 MWPaused / redesign Clermont, OHPJM Jun 2019target 2025
Battery storage project AH2-372, Stephenson County
Battery storage
52.0 MWIn study Stephenson, ILPJM Mar 2022target 2028
Gas project AG2-562, St. Joseph County
Gas · St. Joseph Energy Center, LLC
52.0 MWIn study St. Joseph, INPJM May 2025target 2022
Solar + storage project AH2-199, Will County
Solar + storage
51.7 MWIn study Will, ILPJM Mar 2022target 2026
Solar project AI1-120, Warren County
Solar
51.6 MWIn study Warren, NJPJM Sep 2022target 2025
Solar project AI2-196, Lycoming County
Solar
51.5 MWIn study Lycoming, PAPJM Mar 2023target 2025
Solar project AH1-227, Wise County
Solar · Virginia Electric and Power Company
51.3 MWIn study Wise, VAPJM Feb 2025target 2025
Gas project AH1-703, Bergen County
Gas · Parkway Generation Operating LLC
51.3 MWIn study Bergen, NJPJM Apr 2025
Bergen Generating Station
Gas
51.1 MWAgreement signed Bergen, NJPJM Apr 20162019
Egypt Road Solar
Solar
51.1 MWAgreement signed Dorchester, MDPJM Apr 2016target 2025
Knoxville Solar
Solar
51.0 MWAgreement signed Isle Of Wight, VAPJM Mar 2018target 2027
Hawks Nest Hydro
Hydro
51.0 MWAgreement signed Fayette, WVPJM Mar 2019target 2028
Solar project AI2-244, Nottoway County
Solar
50.3 MWIn study Nottoway, VAPJM Mar 2023target 2028
MC Solar I
Solar
50.0 MWAgreement signed Mercer, PAPJM Mar 2019target 2027
Battery storage project AJ1-001, Mecklenburg County
Battery storage
50.0 MWIn study Mecklenburg, VAPJM Apr 2023target 2028
Battery storage project AG2-370, Allen County
Battery storage · Tillman Storage LLC
50.0 MWIn study Allen, INPJM Mar 2025target 2024
Zion Energy Center - BESS
Battery storage
50.0 MWAgreement signed Lake, ILPJM Nov 2019target 2027
Battery storage project AI2-042, Louisa County
Battery storage
50.0 MWIn study Louisa, VAPJM Feb 2023target 2026
Scioty Solar
Solar
50.0 MWAgreement signed Hardin, OHPJM Sep 2020target 2027
Page 14 of 25

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)