🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New Jersey

GAS · PJM

Bergen Generating Station

Bergen Generating Station is a 51.1 MW gas request with a signed interconnection agreement in the PJM interconnection queue, in Bergen County, New Jersey, connecting to PSEG.

Queue statusConsented
  1. PlanningQueued Apr 2016 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingDec 2019 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AB2-092
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Bergen 138kV
Location
Bergen County, New Jersey
Technology
Gas: 51.1 MW
Total requested
51.1 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
26 April 2016
Proposed online date
June 2027
Came online
December 2019

Location

Marker shows the centre of Bergen County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Bergen County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem