🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New Jersey

GAS · PJM

Gas project Y3-052, Bergen County

Gas project Y3-052, Bergen County is a 50.0 MW gas request built and operating in the PJM interconnection queue, in Bergen County, New Jersey, connecting to PSEG.

Queue statusOperating
  1. PlanningQueued Feb 2013 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingOct 2015 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Y3-052
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Bergen
Location
Bergen County, New Jersey
Technology
Gas: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
28 February 2013
Proposed online date
March 2015
Came online
October 2015

Location

Marker shows the centre of Bergen County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Bergen County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem