Baler LF

Baler LF is a 3.8 MW other request built and operating in the PJM interconnection queue, in Bergen County, New Jersey, connecting to PSEG.

Queue statusOperating
  1. PlanningQueued May 2001 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingMay 2003 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G25
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Marion 26.4kV
Location
Bergen County, New Jersey
Technology
Other: 3.8 MW
Total requested
3.8 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
1 May 2001
Proposed online date
May 2003
Came online
May 2003

Location

Marker shows the centre of Bergen County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Bergen County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem