πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

GAS Β· PJM

Bergen #2

Bergen #2 is a 50.0 MW gas request built and operating in the PJM interconnection queue, in Bergen County, New Jersey, connecting to PSEG.

Queue statusOperating
  1. PlanningQueued Mar 2001 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJun 2002 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G10
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Bergen
Location
Bergen County, New Jersey
Technology
Gas: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
20 March 2001
Proposed online date
June 2002
Came online
June 2002

Location

Marker shows the centre of Bergen County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Bergen County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem