🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in MISO (Midcontinent) — page 11

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,646350.1 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,646 requests · page 11 of 33
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J2991, Wayne County
Battery storage
200 MWIn study Wayne, MIMISO Sep 2022target 2025
Solar project J3170, Avoyelles Parish County
Solar
200 MWIn study Avoyelles Parish, LAMISO Sep 2022target 2026
Solar project J1226, Lenawee County
Solar
200 MWUnder construction Lenawee, MIMISO Apr 2019target 2024
Solar project J2061, Saginaw County
Solar
200 MWIn study Saginaw, MIMISO Aug 2021target 2024
Solar project J2524, Stoddard County
Solar
200 MWIn study Stoddard, MOMISO Sep 2022target 2026
Onshore wind project J1289, Morgan County
Onshore wind
200 MWAgreement signed Morgan, ILMISO Apr 2019target 2024
Battery storage project J3031, Jefferson County
Battery storage
200 MWIn study Jefferson, ILMISO Sep 2022target 2026
Solar project J3449, Pope County
Solar
200 MWIn study Pope, ARMISO Mar 2024target 2028
Onshore wind project J1069, Jasper County
Onshore wind
200 MWUnder construction Jasper, INMISO Mar 2018target 2023
Onshore wind project J2049, Shelby County
Onshore wind
200 MWIn study Shelby, ILMISO Mar 2022target 2025
Battery storage project J2402, Johnson County
Battery storage
200 MWIn study Johnson, ILMISO Sep 2022target 2025
Solar project J2330, Leflore County
Solar
200 MWIn study Leflore, MSMISO Sep 2022target 2026
Battery storage project J2799, Van Buren County
Battery storage
200 MWIn study Van Buren, MIMISO Oct 2025target 2025
Onshore wind project J4193, Meeker County
Onshore wind
200 MWIn study Meeker, MNMISO Oct 2025target 2030
Battery storage project J3296, Hamilton County
Battery storage
200 MWIn study Hamilton, ILMISO Apr 2024target 2027
Solar + storage project J3980, Sullivan County
Solar + storage
200 MWIn study Sullivan, INMISO Apr 2025target 2029
Onshore wind project J1831, Menard County
Onshore wind
200 MWIn study Menard, ILMISO Jun 2020target 2026
Solar project J3944, Bureau County
Solar
200 MWIn study Bureau, ILMISO Feb 2025target 2030
Solar project J2729, West Baton Rouge Parish, La County
Solar
200 MWIn study West Baton Rouge Parish, La, LAMISO Sep 2022target 2025
Battery storage project J2663, White County
Battery storage
200 MWIn study White, INMISO Sep 2022target 2026
Solar project J3601, Morehouse Parish County
Solar
200 MWIn study Morehouse Parish, LAMISO Apr 2024target 2028
Solar project J4073, Coahoma County
Solar
200 MWIn study Coahoma, MSMISO Sep 2025target 2029
Solar project J1581, Nobles County
Solar
200 MWIn study Nobles, MNMISO Apr 2024target 2026
Solar project J2289, Sunflower County
Solar
200 MWIn study Sunflower, MSMISO Sep 2021target 2028
Onshore wind project J1867, Franklin County
Onshore wind
200 MWIn study Franklin, IAMISO Nov 2021target 2025
Battery storage project J3704, Redwood County
Battery storage
200 MWIn study Redwood, MNMISO Apr 2024target 2028
Solar project J3545, Ionia County
Solar
200 MWIn study Ionia, MIMISO Apr 2024target 2028
Solar project J3472, Lapeer County
Solar
200 MWIn study Lapeer, MIMISO Apr 2024target 2028
Solar project J1525, Huron County
Solar
200 MWAgreement signed Huron, MIMISO Jun 2020target 2026
Solar project J1808, Barron County
Solar
200 MWIn study Barron, WIMISO Jun 2020target 2026
Solar project J2089, Mississippi County
Solar
200 MWIn study Mississippi, ARMISO Nov 2021target 2027
Onshore wind project J3324, Palo Alto County
Onshore wind
200 MWIn study Palo Alto, IAMISO Apr 2024target 2029
Solar project J1603, Otsego County
Solar
200 MWAgreement signed Otsego, MIMISO Dec 2021target 2025
Solar project J3974, Jefferson County
Solar
200 MWIn study Jefferson, ARMISO Feb 2025target 2027
Solar project J3434, Kandiyohi County
Solar
200 MWIn study Kandiyohi, MNMISO Mar 2024target 2028
Onshore wind project J2990, Pottawattamie County
Onshore wind
200 MWIn study Pottawattamie, IAMISO Sep 2022target 2025
Solar project J2230, Sullivan County
Solar
200 MWIn study Sullivan, INMISO Mar 2022target 2025
Onshore wind project J1115, Macon County
Onshore wind
200 MWUnder construction Macon, ILMISO Mar 2018target 2024
Battery storage project J3551, Mahaska County
Battery storage
200 MWIn study Mahaska, IAMISO Apr 2024target 2027
Surplus; J944
Battery storage
200 MWIn study New Madrid, MOMISO Aug 2025target 2028
Solar project J1772, White County
Solar
200 MWIn study White, INMISO Jun 2020target 2026
Battery storage project J3236, Chisago County
Battery storage
200 MWIn study Chisago, MNMISO Mar 2024target 2028
Solar project J2672, Shiawassee County
Solar
200 MWIn study Shiawassee, MIMISO Sep 2022target 2025
Solar project J2877, Midland County
Solar
200 MWIn study Midland, MIMISO Sep 2022target 2025
Solar project J3880, Clay County
Solar
200 MWIn study Clay, ILMISO Feb 2025target 2030
Solar + storage project J2238, Maries County
Solar + storage
200 MWIn study Maries, MOMISO Jul 2025target 2024
Solar project J1870, Tangipahoa Parish County
Solar
200 MWIn study Tangipahoa Parish, LAMISO Aug 2021target 2028
Solar project J956, Ralls County
Solar
200 MWAgreement signed Ralls, MOMISO Mar 20182024
Solar project J1460, Rock County
Solar
200 MWUnder construction Rock, WIMISO Apr 2019target 2025
Onshore wind project J1701, Mcdonough County
Onshore wind
200 MWIn study Mcdonough, ILMISO Dec 2021target 2026
Page 11 of 33

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)