United States › Grid › Interconnection queues › Minnesota
ONSHORE WIND · MISOOnshore wind project J4193, Meeker County
Onshore wind project J4193, Meeker County is a 200 MW onshore wind request in interconnection study in the MISO interconnection queue, in Meeker County, Minnesota, connecting to NORTHERN STATES POWER COMPANY.
- PlanningQueued Oct 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2030 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J4193
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- NORTHERN STATES POWER COMPANY
- Connection point (POI)
- SHERBURNE CO
- Location
- Meeker County, Minnesota
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 7 October 2025
- Proposed online date
- December 2030
Location
Marker shows the centre of Meeker County; the queue data does not give exact sites.
Other requests in Meeker County
- Battery storage project J4194, Meeker CountyBattery storage · 500 MW · in study
- Onshore wind project G971, Meeker CountyOnshore wind · 20.0 MW · built
- Onshore wind project G685, Meeker CountyOnshore wind · 20.0 MW · built
- Onshore wind project J625, Meeker CountyOnshore wind · 400 MW · withdrawn
- Onshore wind project J627, Meeker CountyOnshore wind · 400 MW · withdrawn
- Onshore wind project J626, Meeker CountyOnshore wind · 400 MW · withdrawn
- Onshore wind project H050, Meeker CountyOnshore wind · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem