ONSHORE WIND Β· MISO

Onshore wind project H050, Meeker County

Onshore wind project H050, Meeker County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Meeker County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2008 (completed)
  2. Withdrawn / abandonedJun 2012 (project stopped here)
  3. ConsentedJun 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
H050
Grid region
MISO (Midcontinent)
Connection point (POI)
GRE Big Swan 115 kV Substation
Location
Meeker County, Minnesota
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
DPP - SIS
Queue status
Withdrawn
Entered queue
12 June 2008
Agreement signed
26 June 2012
Proposed online date
December 2011
Withdrawn
June 2012

Location

Marker shows the centre of Meeker County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Meeker County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem