United States › Grid › Interconnection queues › Minnesota
ONSHORE WIND · MISOOnshore wind project G971, Meeker County
Onshore wind project G971, Meeker County is a 20.0 MW onshore wind request built and operating in the MISO interconnection queue, in Meeker County, Minnesota.
Request details
- Queue ID
- G971
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- 69 kV line in SE 1/4 of Sec 17 in Cosmos Twp
- Location
- Meeker County, Minnesota
- Technology
- Wind: 20.0 MW
- Total requested
- 20.0 MW
- Study phase
- Network Upgrade
- Queue status
- Operational
- Entered queue
- 13 February 2008
- Agreement signed
- 16 September 2010
- Proposed online date
- November 2009
- Came online
- November 2009
Location
Marker shows the centre of Meeker County; the queue data does not give exact sites.
Other requests in Meeker County
- Battery storage project J4194, Meeker CountyBattery storage · 500 MW · in study
- Onshore wind project J4193, Meeker CountyOnshore wind · 200 MW · in study
- Onshore wind project G685, Meeker CountyOnshore wind · 20.0 MW · built
- Onshore wind project J625, Meeker CountyOnshore wind · 400 MW · withdrawn
- Onshore wind project J627, Meeker CountyOnshore wind · 400 MW · withdrawn
- Onshore wind project J626, Meeker CountyOnshore wind · 400 MW · withdrawn
- Onshore wind project H050, Meeker CountyOnshore wind · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem