United States › Grid › Interconnection queues › Michigan

SOLAR · MISO

Solar project J1603, Otsego County

Solar project J1603, Otsego County is a 200 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Otsego County, Michigan, connecting to METC.

Queue statusConsented
  1. PlanningQueued Dec 2021 (completed)
  2. ConsentedJun 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1603
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Vantyle 138kV
Location
Otsego County, Michigan
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: Not Started
Queue status
Active
Entered queue
3 December 2021
Agreement signed
26 June 2023
Proposed online date
August 2025

Location

Marker shows the centre of Otsego County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Otsego County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem