United States › Grid › Interconnection queues › Louisiana
SOLAR · MISOSolar project J2729, West Baton Rouge Parish, La County
Solar project J2729, West Baton Rouge Parish, La County is a 200 MW solar request in interconnection study in the MISO interconnection queue, in West Baton Rouge Parish, La County, Louisiana, connecting to ENTERGY LOUISIANA.
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Feb 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2729
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY LOUISIANA
- Connection point (POI)
- ADDIS - BIG CAJUN #1 230.0kV
- Location
- West Baton Rouge Parish, La County, Louisiana
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 14 September 2022
- Proposed online date
- February 2025
Location
Marker shows the centre of West Baton Rouge Parish, La County; the queue data does not give exact sites.
Other requests in West Baton Rouge Parish, La County
- Solar project J683, West Baton Rouge Parish, La CountySolar · 50.0 MW · built
- Solar project J1463, West Baton Rouge Parish, La CountySolar · 150 MW · withdrawn
- Solar project J961, West Baton Rouge Parish, La CountySolar · 150 MW · withdrawn
- Solar project J1539, West Baton Rouge Parish, La CountySolar · 146 MW · withdrawn
- Solar project J676, West Baton Rouge Parish, La CountySolar · 50.0 MW · withdrawn
- Solar project J639, West Baton Rouge Parish, La CountySolar · 50.0 MW · withdrawn
- Solar + storage project J1749, West Baton Rouge Parish, La CountySolar + storage · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem