SOLAR Β· MISOSolar project J639, West Baton Rouge Parish, La County
Solar project J639, West Baton Rouge Parish, La County is a 50.0 MW solar request withdrawn in the MISO interconnection queue, in West Baton Rouge Parish, La County, Louisiana, connecting to Entergy.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2017 (completed)
- Withdrawn / abandonedOct 2022 (project stopped here)
- ConsentedDec 2019 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J639
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Entergy
- Connection point (POI)
- Addis - Big Cajun 230kV Line
- Location
- West Baton Rouge Parish, La County, Louisiana
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 16 June 2017
- Agreement signed
- 2 December 2019
- Proposed online date
- November 2020
- Withdrawn
- October 2022
Location
Marker shows the centre of West Baton Rouge Parish, La County; the queue data does not give exact sites.
Power plants in Louisiana Β· Transmission lines in Louisiana
Other requests in West Baton Rouge Parish, La County
- Solar project J2729, West Baton Rouge Parish, La CountySolar Β· 200 MW Β· in study
- Solar project J683, West Baton Rouge Parish, La CountySolar Β· 50.0 MW Β· built
- Solar project J1463, West Baton Rouge Parish, La CountySolar Β· 150 MW Β· withdrawn
- Solar project J961, West Baton Rouge Parish, La CountySolar Β· 150 MW Β· withdrawn
- Solar project J1539, West Baton Rouge Parish, La CountySolar Β· 146 MW Β· withdrawn
- Solar project J676, West Baton Rouge Parish, La CountySolar Β· 50.0 MW Β· withdrawn
- Solar + storage project J1749, West Baton Rouge Parish, La CountySolar + storage Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem