BATTERY STORAGE · MISO

Battery storage project J3704, Redwood County

Battery storage project J3704, Redwood County is a 200 MW battery storage request in interconnection study in the MISO interconnection queue, in Redwood County, Minnesota, connecting to GREAT RIVER ENERGY.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3704
Grid region
MISO (Midcontinent)
Utility / transmission owner
GREAT RIVER ENERGY
Connection point (POI)
Cedar Mountain - Lyon County 345.0kV
Location
Redwood County, Minnesota
Technology
Battery: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
16 April 2024
Proposed online date
September 2028

Location

Marker shows the centre of Redwood County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Redwood County