ONSHORE WIND Β· MISOOnshore wind project J901, Redwood County
Onshore wind project J901, Redwood County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Redwood County, Minnesota, connecting to NORTHERN STATES POWER COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2017 (completed)
- Withdrawn / abandonedMay 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J901
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- NORTHERN STATES POWER COMPANY
- Connection point (POI)
- Lyon County - Cedar Mountain Line
- Location
- Redwood County, Minnesota
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Energy only (ERIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 16 June 2017
- Proposed online date
- October 2021
- Withdrawn
- May 2021
Location
Marker shows the centre of Redwood County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Redwood County
- Battery storage project J4072, Redwood CountyBattery storage Β· 500 MW Β· in study
- Solar project J4152, Redwood CountySolar Β· 250 MW Β· in study
- Solar project J4151, Redwood CountySolar Β· 225 MW Β· in study
- Solar project J2599, Redwood CountySolar Β· 216 MW Β· in study
- Battery storage project J3704, Redwood CountyBattery storage Β· 200 MW Β· in study
- Onshore wind project J2053, Redwood CountyOnshore wind Β· 152 MW Β· in study
- Onshore wind project J1106, Redwood CountyOnshore wind Β· 414 MW Β· withdrawn
- Onshore wind project J3705, Redwood CountyOnshore wind Β· 200 MW Β· withdrawn
- Battery storage project J3665, Redwood CountyBattery storage Β· 100 MW Β· withdrawn
- Onshore wind project H051, Redwood CountyOnshore wind Β· 40.0 MW Β· withdrawn
- Onshore wind project H055, Redwood CountyOnshore wind Β· 40.0 MW Β· withdrawn