United States › Grid › Interconnection queues › Minnesota
SOLAR · MISOSolar project J4151, Redwood County
Solar project J4151, Redwood County is a 225 MW solar request in interconnection study in the MISO interconnection queue, in Redwood County, Minnesota, connecting to MINNESOTA MUNICIPAL POWER AGENCY.
- PlanningQueued Oct 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2030 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J4151
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- MINNESOTA MUNICIPAL POWER AGENCY
- Connection point (POI)
- Cedar Mountain - Lyon County 345.0kV
- Location
- Redwood County, Minnesota
- Technology
- Solar: 225 MW
- Total requested
- 225 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 6 October 2025
- Proposed online date
- May 2030
Location
Marker shows the centre of Redwood County; the queue data does not give exact sites.
Other requests in Redwood County
- Battery storage project J4072, Redwood CountyBattery storage · 500 MW · in study
- Solar project J4152, Redwood CountySolar · 250 MW · in study
- Solar project J2599, Redwood CountySolar · 216 MW · in study
- Battery storage project J3704, Redwood CountyBattery storage · 200 MW · in study
- Onshore wind project J2053, Redwood CountyOnshore wind · 152 MW · in study
- Onshore wind project J1106, Redwood CountyOnshore wind · 414 MW · withdrawn
- Onshore wind project J901, Redwood CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J3705, Redwood CountyOnshore wind · 200 MW · withdrawn
- Battery storage project J3665, Redwood CountyBattery storage · 100 MW · withdrawn
- Onshore wind project H051, Redwood CountyOnshore wind · 40.0 MW · withdrawn
- Onshore wind project H055, Redwood CountyOnshore wind · 40.0 MW · withdrawn
- Onshore wind project H054, Redwood CountyOnshore wind · 40.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem