United States › Grid › Interconnection queues › Minnesota

SOLAR · MISO

Solar project J1581, Nobles County

Solar project J1581, Nobles County is a 200 MW solar request in interconnection study in the MISO interconnection queue, in Nobles County, Minnesota, connecting to NORTHERN STATES POWER COMPANY.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. ConsentedJul 2024 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J1581
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN STATES POWER COMPANY
Connection point (POI)
NOBLES COUNTY
Location
Nobles County, Minnesota
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
17 April 2024
Agreement signed
18 July 2024
Proposed online date
September 2026

Location

Marker shows the centre of Nobles County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Nobles County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem