United States › Grid › Interconnection queues › Minnesota

ONSHORE WIND · MISO

Onshore wind project G385, Nobles County

Onshore wind project G385, Nobles County is a 2.0 MW onshore wind request built and operating in the MISO interconnection queue, in Nobles County, Minnesota.

Queue statusOperating
  1. PlanningQueued Nov 2003 (completed)
  2. ConsentedAug 2005 (completed)
  3. Construction (completed)
  4. OperatingJul 2004 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G385
Grid region
MISO (Midcontinent)
Connection point (POI)
Larkin 24kV
Location
Nobles County, Minnesota
Technology
Wind: 2.0 MW
Total requested
2.0 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
7 November 2003
Agreement signed
29 August 2005
Proposed online date
July 2004
Came online
July 2004

Location

Marker shows the centre of Nobles County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Nobles County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem