🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Minnesota

ONSHORE WIND · MISO

Onshore wind project G162, Nobles County

Onshore wind project G162, Nobles County is a 200 MW onshore wind request built and operating in the MISO interconnection queue, in Nobles County, Minnesota.

Queue statusOperating
  1. PlanningQueued Dec 2001 (completed)
  2. ConsentedMay 2005 (completed)
  3. Construction (completed)
  4. OperatingJun 2003 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G162
Grid region
MISO (Midcontinent)
Connection point (POI)
Fenton Substation
Location
Nobles County, Minnesota
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
3 December 2001
Agreement signed
26 May 2005
Proposed online date
June 2003
Came online
June 2003

Location

Marker shows the centre of Nobles County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Nobles County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem