United States › Grid › Interconnection queues › Minnesota
ONSHORE WIND · MISOOnshore wind project G287, Nobles County
Onshore wind project G287, Nobles County is a 200 MW onshore wind request built and operating in the MISO interconnection queue, in Nobles County, Minnesota.
Request details
- Queue ID
- G287
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Nobles County Substation
- Location
- Nobles County, Minnesota
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Study phase
- SPA - SIS
- Queue status
- Operational
- Entered queue
- 21 January 2003
- Agreement signed
- 24 April 2006
- Proposed online date
- June 2004
- Came online
- June 2004
Location
Marker shows the centre of Nobles County; the queue data does not give exact sites.
Other requests in Nobles County
- Nobles BESSBattery storage · 314 MW · in study
- Solar project J1581, Nobles CountySolar · 200 MW · in study
- SurplusBattery storage · 200 MW · in study
- Onshore wind project J512, Nobles CountyOnshore wind · 250 MW · built
- Onshore wind project G162, Nobles CountyOnshore wind · 200 MW · built
- Onshore wind project G602, Nobles CountyOnshore wind · 32.0 MW · built
- Onshore wind project G374, Nobles CountyOnshore wind · 6.0 MW · built
- Other project G140, Nobles CountyOther · 2.0 MW · built
- Other project G270, Nobles CountyOther · 2.0 MW · built
- Other project G142, Nobles CountyOther · 2.0 MW · built
- Onshore wind project G385, Nobles CountyOnshore wind · 2.0 MW · built
- Onshore wind project J971, Nobles CountyOnshore wind · 250 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem