United States › Grid › Interconnection queues › Minnesota

ONSHORE WIND · MISO

Onshore wind project G287, Nobles County

Onshore wind project G287, Nobles County is a 200 MW onshore wind request built and operating in the MISO interconnection queue, in Nobles County, Minnesota.

Queue statusOperating
  1. PlanningQueued Jan 2003 (completed)
  2. ConsentedApr 2006 (completed)
  3. Construction (completed)
  4. OperatingJun 2004 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G287
Grid region
MISO (Midcontinent)
Connection point (POI)
Nobles County Substation
Location
Nobles County, Minnesota
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
SPA - SIS
Queue status
Operational
Entered queue
21 January 2003
Agreement signed
24 April 2006
Proposed online date
June 2004
Came online
June 2004

Location

Marker shows the centre of Nobles County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota