πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Queue projects under construction in the USA (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown405,125 MW
Active in queue109.2 GW589 requests
Agreement signed64.3 GW347 requests
Withdrawn1,473226.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

40 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1421, East Feliciana Parish County
Solar
300 MWUnder construction East Feliciana Parish, LAMISO Apr 2019target 2024
Solar project J1410, Dane County
Solar
300 MWUnder construction Dane, WIMISO Apr 2019target 2025
Solar project J1226, Lenawee County
Solar
200 MWUnder construction Lenawee, MIMISO Apr 2019target 2024
Solar project J1460, Rock County
Solar
200 MWUnder construction Rock, WIMISO Apr 2019target 2025
Solar project J1325, Rock County
Solar
200 MWUnder construction Rock, MNMISO Apr 2019target 2025
Solar project J1424, Beauregard Parish County
Solar
200 MWUnder construction Beauregard Parish, LAMISO Apr 2019target 2024
Solar project J1299, Scott County
Solar
200 MWUnder construction Scott, MOMISO Apr 2019target 2025
Solar project J1255, Ionia County
Solar
200 MWUnder construction Ionia, MIMISO Apr 2019target 2025
Solar project J1458, Washington County
Solar
200 MWUnder construction Washington, MSMISO Apr 2019target 2024
Onshore wind project J1437, Carroll County
Onshore wind
180 MWUnder construction Carroll, ARMISO Apr 2019target 2024
Solar project J1297, Shiawassee County
Solar
170 MWUnder construction Shiawassee, MIMISO Apr 2019target 2024
Solar project J1224, Washtenaw County
Solar
170 MWUnder construction Washtenaw, MIMISO Apr 2019target 2025
Solar project J1442, Polk County
Solar
165 MWUnder construction Polk, TXMISO Apr 2019target 2025
Solar project J1440, Tunica County
Solar
160 MWUnder construction Tunica, MSMISO Apr 2019target 2024
Solar project J1286, Evangeline Parish County
Solar
150 MWUnder construction Evangeline Parish, LAMISO Apr 2019target 2025
Solar project J1390, Bartholomew County
Solar
150 MWUnder construction Bartholomew, INMISO Apr 2019target 2025
Solar project J1203, Genesee County
Solar
125 MWUnder construction Genesee, MIMISO Apr 2019target 2025
Solar project J1310, Jackson County
Solar
125 MWUnder construction Jackson, MIMISO Apr 2019target 2024
Solar + storage project J1269, Warrick County
Solar + storage
100 MWUnder construction Warrick, INMISO Apr 2019target 2025
Solar project J1239, Ouachita Parish County
Solar
100 MWUnder construction Ouachita Parish, LAMISO Apr 2019target 2024
Solar project J1375, Muskegon County
Solar
100 MWUnder construction Muskegon, MIMISO Apr 2019target 2025
Solar project J1445, Benton County
Solar
100 MWUnder construction Benton, MNMISO Apr 2019target 2025
Solar project J1314, Polk County
Solar
100 MWUnder construction Polk, WIMISO Apr 2019target 2025
Solar project 130, Georgetown County
Solar
100 MWUnder construction Georgetown, SCSoutheast Jul 2019target 2021
Solar project J1219, Tangipahoa Parish County
Solar
100 MWUnder construction Tangipahoa Parish, LAMISO Apr 2019target 2024
Solar project J1426, Benton County
Solar
100 MWUnder construction Benton, MNMISO Apr 2019target 2025
Solar project 135, Georgetown County
Solar
100 MWUnder construction Georgetown, SCSoutheast Dec 2019target 2021
Solar project J1251, Marquette County
Solar
100 MWUnder construction Marquette, MIMISO Apr 2019target 2025
Solar project J1294, Sunflower County
Solar
99.0 MWUnder construction Sunflower, MSMISO Apr 20192024
Solar project J1367, St. Mary Parish County
Solar
95.0 MWUnder construction St. Mary Parish, LAMISO Apr 2019target 2022
SR Metter
Solar
80.0 MWUnder construction Candler, GASoutheast Oct 20192022
Solar project 259, Highlands County
Solar Β· Placid Solar II, LLC
74.9 MWUnder construction Highlands, FLSoutheast May 2019target 2023
Solar project 258, Highlands County
Solar Β· Placid Solar, LLC
74.9 MWUnder construction Highlands, FLSoutheast May 2019target 2023
Solar project 273, Polk County
Solar Β· FL Solar 10, LLC
74.9 MWUnder construction Polk, FLSoutheast Dec 2019target 2022
Solar project 124, Aiken County
Solar
74.0 MWUnder construction Aiken, SCSoutheast Feb 2019target 2025
Battery storage project J1272, Vanderburgh County
Battery storage
50.0 MWUnder construction Vanderburgh, INMISO Apr 2019target 2025
Solar project J1361, Washington Parish County
Solar
50.0 MWUnder construction Washington Parish, LAMISO Apr 20192024
Battery storage project J1257, Tangipahoa Parish County
Battery storage
20.0 MWUnder construction Tangipahoa Parish, LAMISO Apr 2019target 2024
Battery storage project J1329, Washtenaw County
Battery storage
20.0 MWUnder construction Washtenaw, MIMISO Apr 2019target 2025
Other project J1247, St. Mary Parish County
Other
17.0 MWUnder construction St. Mary Parish, LAMISO Apr 20192023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)