SOLAR · MISO

Solar project J1314, Polk County

Solar project J1314, Polk County is a 100 MW solar request under construction in the MISO interconnection queue, in Polk County, Wisconsin, connecting to DAIRYLAND POWER COOPERATIVE.

Queue statusUnder construction
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedAug 2022 (completed)
  3. Construction (current stage)
  4. OperatingTarget Jun 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1314
Grid region
MISO (Midcontinent)
Utility / transmission owner
DAIRYLAND POWER COOPERATIVE
Connection point (POI)
Apple River 161 kV Substation
Location
Polk County, Wisconsin
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Under Construction
Queue status
Active
Entered queue
29 April 2019
Agreement signed
26 August 2022
Proposed online date
June 2025

Location

Marker shows the centre of Polk County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Polk County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem