United States › Grid › Interconnection queues › Indiana
SOLAR + STORAGE · MISOSolar + storage project J1269, Warrick County
Solar + storage project J1269, Warrick County is a 100 MW solar + storage request under construction in the MISO interconnection queue, in Warrick County, Indiana, connecting to Southern Indiana Gas & Electric Company d/b/a Vectren Energy Delivery of Indiana, Inc..
Queue statusUnder construction
- PlanningQueued Apr 2019 (completed)
- ConsentedSep 2025 (completed)
- Construction (current stage)
- OperatingTarget Jul 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1269
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Southern Indiana Gas & Electric Company d/b/a Vectren Energy Delivery of Indiana, Inc.
- Connection point (POI)
- Elliott 69kV Substation
- Location
- Warrick County, Indiana
- Technology
- Solar: 100 MW · Battery
- Total requested
- 100 MW
- Service type
- Energy only (ERIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 29 April 2019
- Agreement signed
- 23 September 2025
- Proposed online date
- July 2025
Location
Marker shows the centre of Warrick County; the queue data does not give exact sites.
Other requests in Warrick County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem