Battery storage project J1272, Vanderburgh County

Battery storage project J1272, Vanderburgh County is a 50.0 MW battery storage request under construction in the MISO interconnection queue, in Vanderburgh County, Indiana, connecting to Southern Indiana Gas & Electric Company d/b/a Vectren Energy Delivery of Indiana, Inc..

Queue statusUnder construction
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedSep 2022 (completed)
  3. Construction (current stage)
  4. OperatingTarget Jul 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1272
Grid region
MISO (Midcontinent)
Utility / transmission owner
Southern Indiana Gas & Electric Company d/b/a Vectren Energy Delivery of Indiana, Inc.
Connection point (POI)
Angel Mound 138kV Substation
Location
Vanderburgh County, Indiana
Technology
Battery: 50.0 MW
Total requested
50.0 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: GIA; Post GIA Status: Under Construction
Queue status
Active
Entered queue
29 April 2019
Agreement signed
2 September 2022
Proposed online date
July 2025

Location

Marker shows the centre of Vanderburgh County; the queue data does not give exact sites.