United States βΊ Grid βΊ Interconnection queues βΊ Indiana
BATTERY STORAGE Β· MISOBattery storage project J1271, Vanderburgh County
Battery storage project J1271, Vanderburgh County is a 100 MW battery storage request withdrawn in the MISO interconnection queue, in Vanderburgh County, Indiana, connecting to Southern Indiana Gas & Electric Company d/b/a Vectren Energy Delivery of Indiana, Inc..
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2019 (completed)
- Withdrawn / abandonedAug 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1271
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Southern Indiana Gas & Electric Company d/b/a Vectren Energy Delivery of Indiana, Inc.
- Connection point (POI)
- Oak Grove 138kV Substation
- Location
- Vanderburgh County, Indiana
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 29 April 2019
- Proposed online date
- July 2022
- Withdrawn
- August 2021
Location
Marker shows the centre of Vanderburgh County; the queue data does not give exact sites.
Other requests in Vanderburgh County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem