United States › Grid › Interconnection queues › Louisiana

OTHER · MISO

Other project J1247, St. Mary Parish County

Other project J1247, St. Mary Parish County is a 17.0 MW other request under construction in the MISO interconnection queue, in St. Mary Parish County, Louisiana, connecting to CLECO POWER.

Queue statusUnder construction
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedMay 2022 (completed)
  3. Construction (current stage)
  4. OperatingApr 2023 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1247
Grid region
MISO (Midcontinent)
Utility / transmission owner
CLECO POWER
Connection point (POI)
Ivanhoe 138kV Substation
Location
St. Mary Parish County, Louisiana
Technology
Other: 17.0 MW
Total requested
17.0 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: Under Construction
Queue status
Active
Entered queue
29 April 2019
Agreement signed
31 May 2022
Proposed online date
October 2021
Came online
April 2023

Location

Marker shows the centre of St. Mary Parish County; the queue data does not give exact sites.

Power plants in Louisiana · Transmission lines in Louisiana

Other requests in St. Mary Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem