🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Indiana

SOLAR · MISO

Solar project J1390, Bartholomew County

Solar project J1390, Bartholomew County is a 150 MW solar request under construction in the MISO interconnection queue, in Bartholomew County, Indiana, connecting to DUKE ENERGY INDIANA.

Queue statusUnder construction
  1. PlanningQueued Apr 2019 (completed)
  2. Consented (completed)
  3. Construction (current stage)
  4. OperatingTarget Aug 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1390
Grid region
MISO (Midcontinent)
Utility / transmission owner
DUKE ENERGY INDIANA
Connection point (POI)
Gallagher Station - Columbus 230 kV Line Tap
Location
Bartholomew County, Indiana
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Under Construction
Queue status
Active
Entered queue
29 April 2019
Proposed online date
August 2025

Location

Marker shows the centre of Bartholomew County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Bartholomew County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem