πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

SOLAR Β· MISO

Solar project J491, Bartholomew County

Solar project J491, Bartholomew County is a 20.0 MW solar request withdrawn in the MISO interconnection queue, in Bartholomew County, Indiana.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2015 (completed)
  2. Withdrawn / abandonedJun 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J491
Grid region
MISO (Midcontinent)
Connection point (POI)
connection to 69 kV Duke line feeding Flat Rock substation
Location
Bartholomew County, Indiana
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
12 November 2015
Proposed online date
May 2017
Withdrawn
June 2017

Location

Marker shows the centre of Bartholomew County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Bartholomew County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem