🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Louisiana

SOLAR · MISO

Solar project J1361, Washington Parish County

Solar project J1361, Washington Parish County is a 50.0 MW solar request under construction in the MISO interconnection queue, in Washington Parish County, Louisiana, connecting to ENTERGY LOUISIANA.

Queue statusUnder construction
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedNov 2021 (completed)
  3. Construction (current stage)
  4. OperatingNov 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1361
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY LOUISIANA
Connection point (POI)
Lagen Holton - Franklinton 115kV Line (J1184)
Location
Washington Parish County, Louisiana
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: Under Construction
Queue status
Active
Entered queue
29 April 2019
Agreement signed
29 November 2021
Proposed online date
January 2024
Came online
November 2024

Location

Marker shows the centre of Washington Parish County; the queue data does not give exact sites.

Power plants in Louisiana · Transmission lines in Louisiana

Other requests in Washington Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem