BATTERY STORAGE Β· MISO

Battery storage project J1906, Washington Parish County

Battery storage project J1906, Washington Parish County is a 100 MW battery storage request withdrawn in the MISO interconnection queue, in Washington Parish County, Louisiana, connecting to ENTERGY LOUISIANA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedMar 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1906
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY LOUISIANA
Connection point (POI)
BOGALUSA
Location
Washington Parish County, Louisiana
Technology
Battery: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 August 2021
Proposed online date
December 2022
Withdrawn
March 2025

Location

Marker shows the centre of Washington Parish County; the queue data does not give exact sites.

Power plants in Louisiana Β· Transmission lines in Louisiana

Other requests in Washington Parish County