Requests shown7913.9 GW
Active in queue13.9 GW79 requests
Agreement signed2,191 MW15 requests
Withdrawn18327.2 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

79 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2519, Richland Parish County
Solar
600 MWIn study Richland Parish, LAMISO Sep 2022target 2026
Solar project J2708, Ouachita Parish County
Solar
500 MWIn study Ouachita Parish, LAMISO Sep 2022target 2027
Solar project J2704, Ouachita Parish County
Solar
500 MWIn study Ouachita Parish, LAMISO Sep 2022target 2027
Solar project J3939, Beauregard Parish County
Solar
386 MWIn study Beauregard Parish, LAMISO Apr 2025target 2030
Solar project J3209, Rapides Parish County
Solar
350 MWIn study Rapides Parish, LAMISO Sep 2022target 2026
Solar project J1598, Calcasieu Parish County
Solar
325 MWAgreement signed Calcasieu Parish, LAMISO Dec 2023target 2026
Solar project J3454, Morehouse Parish County
Solar
300 MWIn study Morehouse Parish, LAMISO Apr 2024target 2028
Solar project J1421, East Feliciana Parish County
Solar
300 MWUnder construction East Feliciana Parish, LAMISO Apr 2019target 2024
Solar project J3014, Rapides Parish County
Solar
280 MWIn study Rapides Parish, LAMISO Sep 2022target 2026
Solar project J1890, Sabine Parish County
Solar
270 MWIn study Sabine Parish, LAMISO Apr 2025target 2027
Solar project J2371, Morehouse Parish County
Solar
250 MWIn study Morehouse Parish, LAMISO Sep 2022target 2026
Solar project J2180, Sabine Parish County
Solar
250 MWIn study Sabine Parish, LAMISO Jul 2022target 2027
Solar project J2317, Ouachita Parish County
Solar
225 MWIn study Ouachita Parish, LAMISO Dec 2021target 2027
Solar project J3479, Rapides Parish County
Solar
225 MWIn study Rapides Parish, LAMISO Apr 2024target 2027
Solar project J4051, Jefferson Davis Parish County
Solar
220 MWIn study Jefferson Davis Parish, LAMISO Sep 2025target 2030
Solar project J4050, Jefferson Davis Parish County
Solar
220 MWIn study Jefferson Davis Parish, LAMISO Sep 2025target 2030
Solar project J2753, East Carroll Parish County
Solar
200 MWIn study East Carroll Parish, LAMISO Aug 2025target 2026
Solar project J2322, Evangeline Parish County
Solar
200 MWIn study Evangeline Parish, LAMISO Nov 2025target 2025
Solar project J3170, Avoyelles Parish County
Solar
200 MWIn study Avoyelles Parish, LAMISO Sep 2022target 2026
Solar project J2729, West Baton Rouge Parish, La County
Solar
200 MWIn study West Baton Rouge Parish, La, LAMISO Sep 2022target 2025
Solar project J3601, Morehouse Parish County
Solar
200 MWIn study Morehouse Parish, LAMISO Apr 2024target 2028
Solar project J1870, Tangipahoa Parish County
Solar
200 MWIn study Tangipahoa Parish, LAMISO Aug 2021target 2028
Solar project J2967, Jefferson Davis Parish County
Solar
200 MWIn study Jefferson Davis Parish, LAMISO Sep 2022target 2025
Solar project J1576, Washington Parish County
Solar
200 MWAgreement signed Washington Parish, LAMISO Mar 2022target 2026
Solar project J2526, Red River Parish County
Solar
200 MWIn study Red River Parish, LAMISO Sep 2022target 2026
Solar project J2224, Iberville Parish County
Solar
200 MWIn study Iberville Parish, LAMISO Aug 2021target 2025
Solar project J1076, St. James Parish County
Solar
200 MWUnder construction St. James Parish, LAMISO Mar 2018target 2022
Solar project J1424, Beauregard Parish County
Solar
200 MWUnder construction Beauregard Parish, LAMISO Apr 2019target 2024
Solar project J1431, St. James Parish County
Solar
200 MWAgreement signed St. James Parish, LAMISO Apr 2019target 2024
Solar project J4092, Beauregard Parish County
Solar
200 MWIn study Beauregard Parish, LAMISO Oct 2025target 2030
Solar project J2228, Concordia Parish County
Solar
200 MWIn study Concordia Parish, LAMISO Dec 2021target 2027
Solar project GEN-2018-050, Caddo Parish County
Solar
200 MWAgreement signed Caddo Parish, LASPP May 2018target 2028
Solar project J1673, Sabine Parish County
Solar
200 MWIn study Sabine Parish, LAMISO Jun 2020target 2025
Solar project J1851, Morehouse Parish County
Solar
185 MWIn study Morehouse Parish, LAMISO Nov 2021target 2026
Solar project J2737, Sabine Parish County
Solar
180 MWIn study Sabine Parish, LAMISO Sep 2025target 2026
Solar project J1583, Iberville Parish County
Solar
175 MWAgreement signed Iberville Parish, LAMISO Jun 2020target 2025
Solar project GEN-2018-106, Caddo Parish County
Solar
165 MWAgreement signed Caddo Parish, LASPP Nov 2018target 2028
Solar project J1669, Jefferson Davis Parish County
Solar
165 MWIn study Jefferson Davis Parish, LAMISO Jun 2020target 2025
Solar project J2714, St. Landry Parish County
Solar
162 MWIn study St. Landry Parish, LAMISO Sep 2022target 2027
Solar project J2651, East Baton Rouge Parish County
Solar
160 MWIn study East Baton Rouge Parish, LAMISO Sep 2022target 2026
Solar project J1286, Evangeline Parish County
Solar
150 MWUnder construction Evangeline Parish, LAMISO Apr 2019target 2025
Solar project J1465, Pointe Coupee Parish County
Solar
150 MWAgreement signed Pointe Coupee Parish, LAMISO Apr 2019target 2024
Solar project J1644, St. Landry Parish County
Solar
150 MWUnder construction St. Landry Parish, LAMISO Jun 2020target 2024
Solar project J2643, Washington Parish County
Solar
150 MWIn study Washington Parish, LAMISO Sep 2022target 2027
Solar project J3781, Jefferson Davis Parish County
Solar
150 MWIn study Jefferson Davis Parish, LAMISO Apr 2024target 2027
Solar project J1794, Acadia Parish County
Solar
150 MWAgreement signed Acadia Parish, LAMISO Jun 2020target 2025
Solar project J4143, West Carroll Parish County
Solar
150 MWIn study West Carroll Parish, LAMISO Oct 2025target 2030
Solar project J3042, St. John The Baptist Parish County
Solar
150 MWIn study St. John The Baptist Parish, LAMISO Sep 2022target 2026
Solar project J2249, Acadia Parish County
Solar
144 MWIn study Acadia Parish, LAMISO Dec 2021target 2027
Solar project J4188, Beauregard Parish County
Solar
140 MWIn study Beauregard Parish, LAMISO Oct 2025target 2029
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)