United States › Grid › Interconnection queues › Louisiana

SOLAR · MISO

Solar project J1431, St. James Parish County

Solar project J1431, St. James Parish County is a 200 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in St. James Parish County, Louisiana, connecting to ENTERGY LOUISIANA.

Queue statusConsented
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedApr 2022 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1431
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY LOUISIANA
Connection point (POI)
Vacherie 230kV Substation
Location
St. James Parish County, Louisiana
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA Complete; Post GIA Status: Not Started
Queue status
Active
Entered queue
29 April 2019
Agreement signed
7 April 2022
Proposed online date
May 2024

Location

Marker shows the centre of St. James Parish County; the queue data does not give exact sites.

Power plants in Louisiana · Transmission lines in Louisiana

Other requests in St. James Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem