🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Louisiana

SOLAR · MISO

Solar project J1142, St. James Parish County

Solar project J1142, St. James Parish County is a 20.0 MW solar request built and operating in the MISO interconnection queue, in St. James Parish County, Louisiana, connecting to ENTERGY LOUISIANA.

Queue statusOperating
  1. PlanningQueued Mar 2018 (completed)
  2. ConsentedJul 2020 (completed)
  3. Construction (completed)
  4. OperatingJul 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J1142
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY LOUISIANA
Connection point (POI)
Vacherie 230kV Substation
Location
St. James Parish County, Louisiana
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: In Service (with Provisional GIA)
Queue status
Operational
Entered queue
12 March 2018
Agreement signed
10 July 2020
Proposed online date
July 2020
Came online
July 2020

Location

Marker shows the centre of St. James Parish County; the queue data does not give exact sites.