United States › Grid › Interconnection queues › Louisiana
SOLAR · MISOSolar project J1644, St. Landry Parish County
Solar project J1644, St. Landry Parish County is a 150 MW solar request under construction in the MISO interconnection queue, in St. Landry Parish County, Louisiana, connecting to CLECO POWER.
Queue statusUnder construction
- PlanningQueued Jun 2020 (completed)
- ConsentedJan 2023 (completed)
- Construction (current stage)
- OperatingTarget Dec 2024 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1644
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- CLECO POWER
- Connection point (POI)
- Champange - Plaisance
- Location
- St. Landry Parish County, Louisiana
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 10 June 2020
- Agreement signed
- 18 January 2023
- Proposed online date
- December 2024
Location
Marker shows the centre of St. Landry Parish County; the queue data does not give exact sites.
Other requests in St. Landry Parish County
- Battery storage project J3840, St. Landry Parish CountyBattery storage · 300 MW · in study
- Battery storage project J4075, St. Landry Parish CountyBattery storage · 300 MW · in study
- Onshore wind project J3368, St. Landry Parish CountyOnshore wind · 200 MW · in study
- Solar project J2714, St. Landry Parish CountySolar · 162 MW · in study
- Onshore wind project J3394, St. Landry Parish CountyOnshore wind · 156 MW · in study
- Solar project J1832, St. Landry Parish CountySolar · 145 MW · built
- Battery storage project J3311, St. Landry Parish CountyBattery storage · 400 MW · withdrawn
- Solar project J1217, St. Landry Parish CountySolar · 200 MW · withdrawn
- Battery storage project J1236, St. Landry Parish CountyBattery storage · 50.0 MW · withdrawn
- Solar project J619, St. Landry Parish CountySolar · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem